Project
Description:
Maintenance
and improvement dredging of a portion of the Federal
navigation channel and Federal maintenance area
in New Bedford Harbor as well as the slip area
located south of the New Bedford State Pier.
Coler
& Colantonio, Inc. provided hydrographic survey
support and control for the project. Efforts included
performing GPS control, project datum verification
surveys, and existing conditions survey of the
entire dredge area.
Special
Considerations:
• Field-to-finish post-processing and plan
generation within 24-hours.
• Volume computations and final plan submittals
within 3 days of performing the survey.
Collaborating Divisions, Completing the Project,
Included:
• Surveying Engineering
Detailed List of Services:
• Control Verification Surveys
• Existing Condition Hydrographic Survey
• Pre-, Interim, and Post-Dredge Surveys
• Plan Submittals
• Volume Computations
• Hydrographic surveys were performed using
a totally automated survey system consisting of
RTK GPS positioning system, digital precision
echosounder, and tide guage interfaced to a ruggedized
notebook computer. Dedicated hydrographic survey
software provided real-time data collection and
navigation.
|
|